The Dholera International airport at Navagam village, Ahmedabad district, is in its final stretch. By July 2026 the runway, taxiway and ATC buildings were complete, the passenger terminal was 75% built, and DGCA licensing was under way. The government expected the airport to start operating within three months of that update.
Gujarat’s newest airfield is no longer a plan on paper. This page tracks every official milestone for Dholera International Airport in one place, and we refresh it whenever something changes. Below you will find the latest Dholera airport status, what has been built so far, and what it all means if you are considering land in Dholera SIR.
Dholera International Airport Status: Live Updates (Newest First)

- 18 October 2026: This hub now brings together our six earlier airport articles. We will add the opening date and first flight here as soon as they are officially announced.
- September 2026: The Ministry of Civil Aviation’s target date for finishing all site work.
- 14 July 2026: Union Civil Aviation Minister K. Ram Mohan Naidu, reported by News On AIR, said overall work was 80% complete. The runway, taxiway and ATC buildings were fully finished, and the passenger terminal stood at 75%. He expected operations within three months and confirmed that MRO hangars are planned for C-295 aircraft. DGCA licensing was in progress.
- June 2026: A trial aircraft landing at the site was reported.
- January–February 2026: Calibration flights were carried out.
- 14 June 2022: The Cabinet Committee on Economic Affairs (CCEA) cleared the project, with Phase 1 costed at about ₹1,305 crore.
- 2012: DIACL was formed as the special purpose vehicle to build and run the airport.
Key Facts About the Dholera International Airport
| Item | Details |
| Official name | Dholera International Airport |
| Site | Navagam village, Ahmedabad district, Gujarat |
| Distance from Dholera SIR core | About 20 km |
| Developer | Dholera International Airport Company Ltd (DIACL) |
| Ownership | AAI 51%, Government of Gujarat 33%, NICDIT 16% |
| Investment | About ₹1,305 crore for Phase 1; about ₹1,712 crore across three phases |
| Runway | Reported as 3,200 m in Phase 1, 4,000 m in later phases |
| Progress (July 2026) | 80% overall; terminal 75% |
| Opening date | To be announced |
| Traffic target, 2026 | 3 lakh passengers; 20,000 tonnes of cargo |
| Traffic target, 20 years | 23 lakh passengers; 2.33 lakh tonnes of cargo |
The traffic targets come from the government’s 2022 projections. They are goals, not actual figures.
Dholera International Airport Location and Connectivity

The airfield sits at Navagam village in Ahmedabad district, roughly 20 km from the core of the special investment region and close to the Ahmedabad Dholera Expressway. The Dholera airport location keeps it within easy reach of both the SIR’s industrial zones and the region’s main highway, so the three are designed to grow as one corridor.
- Road: The expressway is the primary route from Ahmedabad. A dedicated Dholera International airport road is planned to tie the terminal into the expressway and the SIR’s internal network.
- Rail: Rail access forms part of the wider connectivity plan. Our article on the Dholera railway station covers the approved route.
- Metro: Extending Ahmedabad’s metro toward the airport has been proposed. See our explainer on the Ahmedabad Metro Phase 3 route for what is planned and what is still on paper.
Where Construction Stands
Airside is finished. The runway and taxiway were reported 100% complete in July 2026. Phase 1 runway length is reported as 3,200 m, with an extension to 4,000 m planned for later phases. That length determines which aircraft types the airport can handle.
Control and navigation are ready. The air traffic control buildings are complete. Calibration flights in January and February 2026 tested the airport’s systems, and a trial landing was reported in June.
The terminal is the last big piece. At 75% in July, the passenger terminal was the main open item. Interiors, baggage handling and passenger services typically take up the final months of any airport build.
Licensing comes before flights. Every Indian airport needs an aerodrome licence from the Directorate General of Civil Aviation before scheduled services can start. That process was under way in July 2026.
Opening is close but not fixed. The minister’s three-month window points to around October 2026. Until airlines publish schedules, treat any Dholera airport opening date you read online as provisional.
Dholera International Airport Project Timeline
| When | Milestone |
| 2012 | DIACL formed |
| 14 June 2022 | CCEA approval; Phase 1 at about ₹1,305 crore |
| Jan–Feb 2026 | Calibration flights |
| June 2026 | Trial aircraft landing reported |
| 14 July 2026 | 80% complete; terminal 75%; DGCA licensing in progress |
| September 2026 | Site work completion target |
| October 2026 | Operations expected, per the minister’s July statement |
| Next 20 years | Growth towards 23 lakh passengers and 2.33 lakh tonnes of cargo a year |
Dholera International Airport City: Cargo, MRO and Industry

The Dholera smart city airport is meant to do far more than move passengers. Around the airfield, planners envisage an airport city where logistics, aircraft servicing and aviation-linked businesses can set up close to the runway. This is where most long-term employment, and much of the demand for nearby land, is expected to come from.
Cargo. Projected volumes rise from 20,000 tonnes in 2026 to 2.33 lakh tonnes a year within two decades. Air freight suits high-value, time-critical goods such as electronics and precision parts. Manufacturers like the Tata semiconductor plant are the kind of tenants that depend on quick, secure air cargo, which links the airport closely to the SIR’s industrial plans.
MRO. In July 2026, the minister said maintenance, repair and overhaul hangars are planned for C-295 aircraft. MRO work brings skilled technical jobs and a network of specialist suppliers.
Aviation manufacturing. Manufacturing is part of the airport city vision. Until specific companies are allotted land and begin construction, treat “aviation hub” claims as plans rather than facts.
What the Dholera International Airport Means for Plot Buyers
A working airport is one of the clearest signs that a new city is taking shape. It is still one factor among many, and it does not make every nearby plot a sound purchase.
The upside
- Faster travel for businesses, workers and visitors, especially combined with the expressway.
- New jobs at the terminal, in cargo and in MRO, all creating demand for homes, schools and shops.
- A stronger pitch for industry, since exporters weigh air links heavily when choosing a location.
The watch-outs
- Dates can slip. Don’t pay a premium that assumes flights start on a particular day.
- Targets are not traffic. Three lakh passengers a year is a modest start; the big numbers are two decades away.
- Rules near runways. Plots close to an airfield can face height limits and noise-related land-use restrictions. Check the zoning in the Dholera SIR development plan.
- Documents first. Confirm clear title, NA status, the town planning scheme and RERA registration where applicable.
Our take: with a five to ten year horizon and properly checked paperwork, a well-placed plot can share in the airport city’s growth. If you need quick returns, weigh the risks above more heavily than the headlines.
FAQs on Dholera International Airport
As of July 2026, work was 80% complete: runway, taxiway and ATC buildings were finished, the terminal was 75% built, and DGCA licensing was in progress.
The minister said in July 2026 that operations would begin within three months, which points to around October 2026. The official opening date and first flight are yet to be announced.
At Navagam village in Ahmedabad district, Gujarat, about 20 km from the Dholera SIR core and near the Ahmedabad–Dholera Expressway.
The site is reached from Ahmedabad city via the Ahmedabad–Dholera Expressway. We will add the official distance and travel time once published.
DIACL, a special purpose vehicle set up in 2012 and owned by AAI (51%), the Government of Gujarat (33%) and NICDIT (16%).